A new extrusion blow molding machine arrives with a factory acceptance test certificate, a parameter book and a set of drawings. Three weeks later it is running, but nobody can say which parameters were settled on, which settings were changed during the night shift to get a stubborn part to release, or whether the machine ever ran continuously for long enough to prove it can hold a dimension. That is how a commissioning project becomes a warranty argument.
The cost of an informal commissioning is paid twice. First, a defect that would have been visible during a structured dry run — a chattering cylinder, a slow pressure build on a long air main, a temperature zone that hunts instead of holding — is absorbed into production and blamed on the material. Second, when something fails in month eight, there is no documented baseline to compare against, so every conversation about root cause starts from scratch and every claim about performance is unprovable.
Sailwin has built extrusion blow molding machines for 15+ years, with 500+ machines delivered into 60+ countries, CE marking, ISO 9001:2015 manufacturing and a 2-year whole-machine warranty, running from 0.5 L to 1000 L container capacity. Every machine is load-tested at the factory before shipment, and on-site installation and commissioning typically take 3 to 7 days with 7×24 remote support afterwards. This article sets out the commissioning sequence that protects both the machine and the warranty, and the evidence each stage should leave behind.
Key Takeaways
- Commissioning runs in a fixed order — installation and utilities, dry run without material, first parison, mould trial, capability run, handover. Skipping the dry run only moves the discovery to a later and more expensive stage.
- Every stage should produce a document. Utility readings, interlock checks, the parameter sheet and the capability run log are the evidence base for warranty claims and for every future optimisation project.
- A factory acceptance test is not on-site commissioning. FAT proves the machine at the factory under load; it does not prove your foundation, your air supply, your chilled water temperature or your operators.
Send Your Machine Model and Site Conditions for a Commissioning Plan
Share the container size, material and utility data — our engineers return the commissioning sequence, the utility envelope and the documents you should receive at handover.
1. Why Commissioning Order Matters More Than Commissioning Speed
Extrusion blow molding machine commissioning is a sequence, not a checklist, and the order carries information. A dry run performed before any material is loaded isolates mechanical and electrical behaviour: valve timing, clamp motion, pressure build, temperature control. Once resin is in the machine, the same faults produce defects instead of clean measurements, and the engineer has to separate machine behaviour from material behaviour at the same time.
That distinction matters commercially. Most warranty disputes on blow molding machines are not about component failure; they are about whether a machine ever met its specification. A plant that commissioned informally has no answer, because the only figure anyone recorded was the cycle shown on the HMI on the day the last engineer left.
There are four conditions a commissioning sequence exists to establish, and each one has a stage where it is proven:
- The machine is mechanically and electrically sound before material is introduced, established during the dry run.
- The utilities are inside the machine’s envelope — air pressure, chilled water temperature, power quality — established during installation.
- The process can make a good part repeatedly, established during the mould trial and capability run.
- The plant can reproduce that process without the commissioning engineer, established at handover and training.
2. The Commissioning Sequence Stage by Stage
| Stage | What is proven | Evidence to keep |
|---|---|---|
| 1. Pre-installation utility check | Foundation, level, power supply, compressed air at 30–40 bar high pressure and 8–10 bar low pressure, chilled water at 8–12 °C | Logged readings per utility, signed against the machine’s requirement sheet |
| 2. Mechanical installation and alignment | Alignment, clamping parallelism, guard and interlock function, CE conformity in place | Alignment record, interlock test sheet |
| 3. Dry run without material | Full cycle motion, valve and cylinder response, pressure build and decay, heating zones holding setpoint | Cycle log, temperature trend from the controller, list of corrections made |
| 4. First parison and material run-in | Extrusion stability, melt temperature, die gap and screw recovery producing a repeatable parison | Parison weight and length records at agreed intervals |
| 5. Mould trial and parameter development | The process window for this mould: blow pressure, wall thickness distribution, cooling, deflashing | The parameter sheet for the part, saved in the controller per mould |
| 6. Capability run | Continuous operation at target rate with dimensions and weight inside specification | Signed run log: duration, output, reject count, measured dimensions |
| 7. Handover and training | Operators can start, stop, change parameters and change a mould without supervision | Handover pack, training attendance list, warranty registration |
Sailwin schedules on-site installation and commissioning at 3 to 7 days for a standard machine, which is enough time for all seven stages when the utilities are ready before the machine arrives. The single most common cause of an overrun is not the machine: it is a compressed air supply that reaches 25 bar instead of the 30–40 bar the blowing system expects, discovered on the day the first parison is due.
3. The Dry Run: What to Prove Before Material Goes In
The dry run is the stage most often compressed to save a day, and it is the cheapest day in the whole project. With no resin in the machine, every observation is unambiguous. Cylinder motion is either smooth or not. The blow valve either opens and closes cleanly or chatters. Mold closing and clamping either build tonnage progressively or shock the frame. Heating zones either hold setpoint or hunt.
Cycle the machine through a complete sequence repeatedly and watch three things. First, valve and cylinder response — Sailwin machines use FESTO combi blow valves and SMC cylinders, and sluggishness at this stage is a pneumatic supply problem, not a valve problem. Second, pressure build and decay on the blowing circuit; a slow build is almost always an undersized or long air main, and it will look like a mould problem once parts are being made. Third, temperature control, which should hold about ±1 °C with barrel heating in the 90–115 °C band for typical polyolefins.
Record what you changed. The corrections made during a dry run are the first entries in the machine’s history and belong in the handover pack. One pattern stands out across 500+ delivered machines: machines with a written dry-run record spend less time in the first year chasing intermittent faults, because a comparison between “as commissioned” and “as found” exists.
A warranty covers components. It does not cover a process that was never defined. The parameter sheet you sign at handover is the document that makes both the warranty and every later optimisation project possible.
Get a Commissioning Checklist for Your Machine and Mould
Send the container size, material and mould details — we return the stage-by-stage commissioning plan, the utility envelope and the parameter sheet template your operators will use.
4. Mould Trial, Capability Run and Handover
The mould trial develops the process window for one specific part. Die gap and screw recovery are set against measured parison weight and wall distribution rather than by eye, melt temperature is set as low as the material’s processing window and weld line quality allow, blow pressure is established within the 25–40 bar range, and cooling is tuned until the part leaves the mould straight and stable. Every one of those decisions has a number behind it, and the numbers belong in the controller, saved per mould.
The capability run is where commissioning turns from opinion into evidence. Run the machine continuously at the target rate for a defined period with the actual material and the actual mould, and measure the output rather than watching it. Record cycle time, container weight at intervals, critical dimensions, wall thickness distribution and the reject count with the reason for each reject. That record is what a supplier and a customer can both sign, and it is the baseline against which every future complaint is judged.
Handover decides whether the plant needs the commissioning engineer again next week. Walk the operators through a real task: change a parameter and change it back, change a mould, start from cold, and interpret an alarm. Sailwin machines log 40+ parameters in real time, so training should include where that history lives and how to export it. A plant that can send a parameter history over 7×24 support channels gets a faster answer than one describing symptoms by telephone.
5. Case Study: A 30 L Machine Commissioned Without a Dry Run Record
A supplier of industrial containers took delivery of a machine for 30 L parts and put it straight into production. Weight variation appeared in week two and was attributed to the material.
- Container weight drifting outside the tolerance band within the first fortnight
- No parameter baseline recorded, so drift could not be distinguished from a bad original setting
- Blowing pressure taking longer to build on one mould station, initially blamed on the mould
- A structured commissioning pass performed retrospectively: utility readings, dry-run cycle check, then material run-in
- Air supply measured at the machine inlet and the blowing circuit timed from valve signal to full pressure
- Parison weight and wall distribution re-established with the wall thickness controller, melt temperature set within the material’s window
- Parameter sheet created and saved per mould, with the controller history exported as the baseline record
- The cause was a utility, not the material, and it was found by measurement rather than by substitution of resin grades
- Weight came back inside the band once parison control and melt temperature were re-established against the specification
- A baseline now exists, so the next drift can be compared against a documented start point instead of being argued about
Scenario based on a Sailwin customer project; site-specific figures available on request during engineering review.
Frequently Asked Questions
Commission the Machine Once, Properly, With a Signed Baseline
Send your bottle drawing, container sample or target output. Our engineering team replies with a machine recommendation, mould assessment and factory-direct quotation within 24 hours.
Related Reading:
• Extrusion Blow Molding Machines from 0.5 L to 1000 L
• Planned Maintenance Schedule for EBM Machines
• HDPE, PP and PA Material Selection for Blow Molding
• What an Extrusion Blow Molding Machine Costs
• Screw and Barrel Wear Diagnosis
• Jerrycan Blow Molding Machines




