x
Send Your Inquiry Today
Quick Quote

From Order to Production: Shipping and Installation Timeline

Navigation: Home / PET Blow Molding Machine / Shipping and Installation
Updated: 2026 Technical Guide · By Sailwin Engineering Team

A PET blow molding machine installation schedule is usually written by the supplier and then quietly broken by the site. The machine arrives on time, but the concrete is not cured, the electrical feed is not terminated, or the compressed air ring main is not pressure tested. The result is a machine sitting in its crate for two weeks while the launch date moves. The difficult part is that none of it is unusual, and all of it is preventable.

The typical failure points are consistent. Utility capacity was assumed rather than measured, so the high-pressure air supply cannot hold pressure at the nozzle. The mould store was not positioned for the intended changeover time, so the fast-change capability of the machine is never realised. Operator training was treated as an afterthought, so the line runs in manual for months. Or the factory acceptance test was skipped in the interests of speed, so problems that should have been solved in the supplier’s plant are solved in yours.

Sailwin has delivered PET stretch blow molding machines into 500+ installations across 60+ countries over 15+ years, with CE-marked machines built under ISO 9001:2015 and a 2-year whole-machine warranty. This guide sets out what happens between the purchase order and the first saleable bottle, who owns each stage, and which stages have the least slack in them.

Key Takeaways

  • Machine supply is rarely the critical path: standard configurations are built in 30–45 days, with custom builds at 45–60 days. Civil works, electrical capacity and utility installation usually take longer than that — so start them in parallel with the machine build, not after the machine arrives.
  • On-site work is short if the site is ready: installation and commissioning take 3–7 days. That figure assumes the machine can be moved into position, powered, and connected to tested high-pressure air and chilled water on day one. If it cannot, the same work takes weeks.
  • The factory acceptance test is your only cheap correction window: every Sailwin machine is full-load FAT tested before shipment. Corrections made in the supplier’s plant are free; corrections made in yours are not.

Planning a PET Line Launch Date?

Send your target start-up date and container specification — we return a machine lead time and site-readiness checklist within 24 hours.

1. The Full Timeline, Stage by Stage

The table below sets out the sequence from order to production, with the duration each stage normally needs and the party that owns it. The right-hand column is the one worth reading twice: it lists what actually slips in practice, which is almost never the machine itself.

StageTypical durationOwnerWhat usually slips
Order, drawing approval and mould designFront end of the build windowBuyer and supplier togetherLate decisions on neck finish, decoration or mould layout, which restart part of the design work
Machine build30–45 days standard; 45–60 days for custom configurationsSupplierConfiguration changes after the order is released, which reset the lead time rather than extend it
Factory acceptance testFull-load running test before shipmentSupplier, with buyer attendance recommendedBuyer absence, which means the acceptance criteria are never formally agreed
Crating, documentation and sea freightAdds transit time on top of the build window, and is destination-dependentSupplier for packing; buyer for import clearanceImport documentation and customs clearance, which are outside the supplier’s control entirely
Site preparationShould run in parallel with the build, not after itBuyerConcrete curing, electrical feed termination and pressure testing of air and water mains
Installation and commissioning3–7 daysSupplier engineers, with buyer utilities supportUtilities that were signed off as ready but cannot hold pressure or temperature under load
Operator training and handoverOverlaps the commissioning windowSupplier and buyer jointlyOperators assigned late, so the machine runs below its capability for the first months

2. Factory Acceptance Testing: The Cheap Correction Window

Every Sailwin machine is full-load tested before shipment. That matters commercially more than technically: a correction made in the supplier’s plant costs the supplier time, while the same correction made on your site costs you time, and your time is the one that has a launch date attached to it.

To get value from the FAT, agree the acceptance criteria in advance and run the test on the container you actually intend to produce, not on a convenient sample. The test should demonstrate the machine meeting its stated output on your bottle, with the heating profile recorded and wall thickness measured at defined points. Ask for the process parameters to be recorded at the end of the test, because that record becomes the reference for the first production run on your site.

If you cannot attend in person, ask for video evidence and a written process record rather than a statement that the test was passed. The distinction matters later, when a wall thickness question arises and there is nothing to compare against.

A factory acceptance test is not a formality at the end of the build. It is the reference data set that every later production decision on your site will be measured against.

3. Crating, Shipping and Import Documentation

Large machinery travels by sea in a manner that has to be planned: the machine is protected against moisture and movement, and the moulds and loose components are packed so that nothing shifts against a machined surface. The container is loaded at the supplier’s plant after the FAT, so the process sequence is test, then crate, then ship — never the reverse.

On the documentation side, the standard set for an export shipment of industrial machinery typically includes the commercial invoice, packing list, bill of lading, certificate of origin and the CE declaration of conformity, plus any phytosanitary treatment certificate required for wooden packing materials in your destination market. Import clearance is the buyer’s responsibility and is the single largest source of schedule variance outside the supplier’s control, so the documentation set should be reviewed by your customs broker before the container is loaded rather than after it arrives.

Two practical points reduce risk at the destination. First, confirm that the shipping configuration matches what your site can receive — a large machine may need a crane or a heavy forklift on arrival, and that equipment should be arranged before the vessel berths, not after. Second, verify that lifting points and centre-of-gravity information are supplied with the packing documentation, because rigging a blow moulding machine by guesswork is how machines get damaged before they are ever switched on.

Import Documentation and Shipping Checklist

Send your destination port and incoterm — we return the shipping configuration, documentation list and rigging requirements within 24 hours.

4. Case Study: Holding a Launch Date Through a Long-Lead Build

A bottler commissioning a new PET line had a contracted retail launch date that could not move, and a building that was still under construction when the machine order was released.

CLIENT CHALLENGE

  • Fixed retail launch date with no flexibility, and a greenfield building still under construction
  • High-pressure air, chilled water and electrical supply all still to be installed when the machine order was placed
  • Operators to be recruited and trained before the first production run
OUR SOLUTION

  • Site readiness checklist issued with the order, so civil, electrical and utility works ran in parallel with the 30–45 day build window rather than after it
  • Utility specification fixed at the enquiry stage: high-pressure air at 30–40 bar, low-pressure air at 8–10 bar on a separate main, and chilled water at 8–12 °C, so the contractors sized their mains from one document
  • Full-load FAT completed before crating, with the process parameters recorded and issued as the starting recipe for the site run
  • Installation and commissioning planned into a 3–7 day window, with training delivered during the same period so operators were present for the first production runs
OUTCOME AND VALUE

  • Utilities ready before arrival, so the commissioning window was used for commissioning instead of for construction
  • Start-up from a recorded baseline, because the FAT process parameters were carried to site as the first production recipe
  • Trained operators at handover, which shortens the period before the line reaches its rated output

Scenario based on a Sailwin customer project; site-specific figures available on request during engineering review.

5. Site Preparation: What Must Be Ready on Day One

The 3–7 day commissioning window is achievable only if every item below is complete before the machine is uncrated. Work through it as a signed checklist, not as a set of assumptions, because each item is cheap to complete early and expensive to complete in a hurry.

ItemReady-state testConsequence if not ready
Foundation and floor loadingCured, level and checked against the installation drawing for the specific modelMachine cannot be positioned or levelled; every subsequent step waits
Electrical supply and terminationTerminated, labelled and megger-tested to the machine’s requirement, with correct protection devices fittedNo power, therefore no commissioning; a late capacity upgrade can add weeks
High-pressure airCompressor capable of 30–40 bar, receiver in place, main pressure-tested and able to hold pressure at the machine with the blow valve firingProduction cannot start; pressure drop shows up as inconsistent wall thickness rather than a simple fault
Low-pressure airIndependent main at 8–10 bar for ancillary functions, not shared with the high-pressure circuitAncillary functions pull pressure down during blowing, destabilising the process
Chilled waterChiller sized for the mould load, delivering 8–12 °C at the mould with flow verified at every circuitCycle time cannot be met and wall thickness distribution becomes unstable
Mould store and handlingStorage within the production area, with lifting equipment available for mould and preform handlingThe machine’s under-30-minute mould change will not be achievable in practice
Preform supply and storageQualified preforms on site, stored closed and clean, with enough stock to run the commissioning trialsCommissioning runs on substitute preforms, which invalidates the wall thickness baseline

6. Commissioning, Training and Handover

Commissioning is not finished when the machine produces a good bottle. It is finished when the machine produces good bottles repeatably, with the process parameters documented, and when the operators can run and adjust it without a supplier engineer standing beside them. Aim the 3–7 day window at that standard rather than at the first acceptable sample.

The technical content of handover should include the heating profile and the recorded process parameters from the FAT, the wall thickness measurement procedure with defined measurement points, the mould change procedure with a target time, and the daily checks that keep the machine within its window. Sailwin machines monitor 40+ process parameters in real time through the PLC, so the handover should also cover which parameters to watch and what their normal ranges are.

Two further points affect the first months of operation. Sailwin machines use Siemens or Mitsubishi PLC control with FESTO combined blowing valves, SMC cylinders and Schneider electrical components, and PID control holds the heating zone within ±1 °C — which is the reason preform heating is repeatable enough to be documented. Servo-driven machines reduce power consumption by up to 30% and high-pressure exhaust recovery reduces compressor load by roughly 20%, so the utility consumption figures recorded during commissioning become the baseline you later measure against. After handover, common wear parts are dispatched within 48 hours and remote support is available 7×24, with a 2-year whole-machine warranty covering the machine itself.

Frequently Asked Questions

How long does it take from order to production for a PET blow molding machine?
Build time is 30–45 days for standard configurations and 45–60 days for custom builds, followed by crating and sea freight, then 3–7 days for on-site installation and commissioning. The machine is rarely the critical path. Site preparation, electrical capacity and utility installation usually take longer than the build, so start them in parallel with the order rather than after the machine arrives.
What is a factory acceptance test and do I need to attend?
It is a full-load running test of the machine before shipment, performed on the container you intend to produce. Every Sailwin machine is FAT tested. Attending is strongly recommended, because corrections in the supplier’s plant cost the supplier time while the same corrections on your site cost you launch time. If you cannot attend, request video evidence and the recorded process parameters in writing.
How long does installation and commissioning take?
Sailwin schedules 3–7 days for installation and commissioning. That figure assumes the machine can be moved into position, powered, and connected to pressure-tested high-pressure air and chilled water immediately. If any utility is not ready, the same work extends by however long the civil or electrical repair takes, which is why site readiness should run in parallel with the machine build.
What utilities must be ready before the machine arrives?
A cured and level foundation checked against the installation drawing, a terminated and tested electrical supply, a high-pressure air system capable of 30–40 bar with the receiver in place and the main pressure-tested, a separate low-pressure main at 8–10 bar for ancillary functions, and chilled water delivered at 8–12 °C with flow verified at every mould circuit. Mould storage, lifting equipment, and qualified preforms should also be on site.
Why does the compressed air supply matter so much at start-up?
PET blowing needs high-pressure air at 25–40 bar supplied from a compressor rated 30–40 bar. If the main is undersized or leaks, pressure at the nozzle collapses when the blow valve fires, and the symptom is inconsistent wall thickness rather than an obvious fault. Ancillary functions should be on a separate 8–10 bar main so they cannot pull pressure down during a blow.
What documents are needed to ship a blow molding machine?
The standard set for exporting industrial machinery typically includes the commercial invoice, packing list, bill of lading, certificate of origin and the CE declaration of conformity, plus any phytosanitary treatment certificate required for wooden packing in your destination market. Import clearance is the buyer’s responsibility and is the largest source of schedule variance outside the supplier’s control, so have your customs broker review the set before the container is loaded.
What should operator training cover during commissioning?
The recorded process parameters from the factory acceptance test, the heating profile, the wall thickness measurement procedure with defined measurement points, the mould change procedure with its target time, and the daily checks that keep the machine in its operating window. Because the PLC monitors 40+ parameters in real time, training should also cover which parameters to watch and what their normal ranges are.
What support is available after the machine is installed?
Sailwin machines carry a 2-year whole-machine warranty, with CE marking and production under ISO 9001:2015. Common wear parts are dispatched within 48 hours and remote support is available 7×24. Before handover, record the utility consumption and process parameters from commissioning, because those become the baseline against which later drift is measured.
SAILWIN MACHINERY · FACTORY DIRECT

Start Site Work Before the Machine Leaves the Factory

Send your bottle drawing, container sample or target output. Our engineering team replies with a machine recommendation, mould assessment and factory-direct quotation within 24 hours.

Scroll to Top
WeChat
WeChat:
Sailwin-Amy
WeChat QR
WhatsApp